Matering & Regulation Station Project (EPC)
Project | : | Matering & Regulation Station Project (EPC) |
Client | : | Amata B.Grimm Power 3 project / PTT |
Period | : | Feb 2011 - Feb 2012 |
Value | : | 83 MB |
Alcan G3 (Evaporator)
Project | : | Alcan G3 (Evaporator) | ||||
Client | : | Alcan Gove Development Pty Limited. | Piping Work | : | 12,000 | di |
Period | : | Oct 2005 - Apr 2006 | Steel Structure and Duct Work | : | 750 | tons |
Value | : | 120 MB | Equipment Installation | : | 1,400 | tons |
Alcan G3 (High Temperature Digester Plant)
Project | : | Alcan G3 (High Temperature Digester Plant) | ||||
Client | : | Alcan Gove Development Pty Limited. | Piping Work | : | 120,000 | di |
Period | : | Apr 2006 - Aug 2006 | Steel Structure and Duct Work | : | 750 | tons |
Value | : | 360 MB | Equipment Installation | : | 1,400 | tons |
C4175-EGTL Nigeria Chevron Module Supply
Project | : | C4175-EGTL Nigeria Chevron Module Supply |
Client | : | Air Products PLC. |
Period | : | Sep 2006 - Jul 2007 |
Value | : | 220 MB |
Vincent FPSO
Project | : | Vincent FPSO | ||||
Client | : | Vecto Aibel Limited. | Piping Work | : | 40,000 | di |
Period | : | Sep 2006 - Aug 2007 | Steel Structure and Duct Work | : | 800 | tons |
Value | : | 55 MB | Equipment Installation | : | 550 | tons |
Windmill-ABT (Viny Thai)
Project | : | Windmill-ABT (Viny Thai) | ||||
Client | : | Toyo-Thai Corporation Public Co., Ltd. | ||||
Period | : | Dec 2010-Sep 2011 | ||||
Value | : | 120 MB |
ATC Reformer & Aromatic Complex II
Project | : | ATC Reformer & Aromatic Complex II | ||||
Client | : | SKEC (Thai) | Piping Work | : | 200,000 | di |
Period | : | Oct 2006 - Feb 2008 | Equipment Installation | : | 1,530 | tons |
Value | : | 134 MB |
RRC Upgrading Project (Mechanical & Piping Works)
Project | : | RRC Upgrading Project (Mechanical & Piping Works) |
Client | : | SKEC (Thai) |
Period | : | Mar 2008 - Dec 2008 |
Value | : | 240 MB |
MOC Cracker
Project | : | MOC Cracker | ||||
Client | : | Samsung Engineering (Thailand) Co., Ltd. | Piping Work | : | 248,000 | di |
Period | : | Nov 2007 - Oct 2009 | Steel Structure and Duct Work | : | 1,400 | tons |
Value | : | 222 MB | Equipment Installation | : | 4,965 | tons |
PTT Ethane Separation Plant (ESP)
Project | : | PTT Ethane Separation Plant (ESP) | ||||
Client | : | Samsung Engineering (Thailand) Co., Ltd. | Piping Work | : | 540,000 | di |
Period | : | May 2008 - Dec 2009 | Pipe Support Work | : | 80 | tons |
Value | : | 830 MB | Steel Structure and Duct Work | : | 6,000 | tons |
Equipment Installation | : | 12,000 | tons |